Found 14 Results - Page 1 of 1
Day 78: That’s a wrap! Three days ahead of schedule, 60 flats in Burton are now cosy and warm, with their tenants delighted with their r
Day 55: Chestnut Mews complete & a visit from DECC The final commissioning of the 30 flats in Chestnut Mews happened today, witnessed by a
Day 51: Commissioning So far 24 flats have been commissioned and left running and 30 will have been commissioned by the end of the week. The en
Day 42: First Installations The first flats are receiving their installations today. The installation teams are operatives from J Tomlinson wh
Task: Scaffolding Today operatives from All Round Scaffolding erected the scaffold at Chestnut Mews.
Task: Drilling phase nearing completion Drilling has progressed well and to schedule, despite difficult ground conditions.
Task: Drilling continues Drilling continues with the rigs working on the final two arrays at Chestnut Mews.
Task: Headering This task involved connecting the individual boreholes up to their communal arrays.
Task: Tenant liaison Today we continued the tenant liaison process, meeting with Mr and Mrs Tropman of 30 Chestnut Mews.
Task: Drilling – update Drilling continues at a pace having completed seven boreholes to date, and another two being drilled on day eigh
Task: Drilling – first complete borehole The first ground loop was installed at 10:30am by lead driller Shaun Crozier and his team from G
Task: Drilling We are on site at Chestnut Mews, and have commenced drilling the communal borehole array.
Task: Drilling preparations Today’s on site activity at Trent & Dove Housing’s 60-flat heating upgrades scheme saw site mobil
Follow a real-life ground source heat pump retrofit project as Kensa Heat Pumps and Trent & Dove Housing share regular live blog feeds documenting